This week I continued with the modelling of the base form work and slab section. Below I have added in a few screen shots of where I am up to.








In the above photos I have shown where I am currently up to with the modelling of the base concrete slab. So far in these progress shots I have used 3dsMax to model the formwork in the strip footings and the water proof sheeting. A few measurements may need to be adjusted but will wait until it has been tested out in the cryEngine. In the above photos the framing and form work have been put in place as well as the water proof sheeting. Next up will be the rest of the formwork in the slab.

As a group in yesterdays class we had a discussion and decided that in order to speed up this modelling process we each needed to take on a role in the modelling stage. Having this discussion has changed our whole time line for the project. We have categorised the modelling into different parts and they are as follows:
  • Base Structure and other elements
  • Internal Stud walls
  • External Walls
  • Flooring
  • Roofing